NNPC says it raised $1.5 billion for the AKK gas pipeline against its projected throughput, and targets gas to Abuja by year end

Key findings

  1. NNPC said it raised about $1.5 billion for the AKK gas pipeline based solely on the gas the line is projected to carry.
  2. The project is about 95% complete; NNPC targets gas to Abuja before the end of 2026 and to Kaduna and Kano in 2027.
  3. The pipeline is designed to carry up to 2.2 billion standard cubic feet of gas a day, Leadership and Daily Trust reported.
  4. Domestic gas sales averaged 2.14 billion standard cubic feet a day in August, NUPRC's provisional figures show.

NNPC Limited has raised $1.5 billion to finance the Ajaokuta-Kaduna-Kano (AKK) gas pipeline, its group chief executive Bayo Ojulari told the News Agency of Nigeria, in remarks ThisDay and Arise reported on 16 November. The money was raised against the volumes of gas the pipeline is expected to transport, rather than on government guarantees or the cash flows of oil fields.

Audu Ibrahim, managing director of NNPC Gas Infrastructure Company, repeated the figure at a pipeline conference in Abuja this week. "We raised about $1.5 billion based solely on projected pipeline throughput," he said, according to Leadership. NNPC did not name the lenders or the terms in the reports.

Ojulari said the main line is finished and the project about 95% complete, with the remaining work on stations and the links to users. NNPC aims to deliver gas to Abuja before the end of 2026 and to Kaduna and Kano in 2027. Daily Trust reported that the pipeline is valued at about $2.8 billion, and both Daily Trust and Leadership put its design capacity at up to 2.2 billion standard cubic feet of gas a day. The outlets gave different lengths for the line, so this piece does not state one.

What Dataminal's data shows

NUPRC's provisional figures for August, which Dataminal carries, put Nigeria's gas production at 7.92 billion standard cubic feet a day, 8.12% more than a year earlier. Domestic sales averaged 2.14 billion standard cubic feet a day, 26.97% of production; a larger share went to export. At full capacity AKK alone could carry about as much gas as the whole domestic market now buys, which is why its users in the north (power plants, fertiliser makers and factories) matter to how fast it fills.

Gas production
7.92 bscf/d
August 2026, provisional
Domestic gas sales
2.14 bscf/d
August 2026, provisional
AKK design capacity
2.2 bscf/d
As reported
Source: NUPRC via Dataminal; capacity as Leadership and Daily Trust reported

Why it matters

Financing a pipeline on its expected throughput moves the cost of gas infrastructure off the public budget and onto the project's own revenue, the model pipeline operators at the conference called for. It also ties the lenders' return to how much gas actually flows north, so connecting buyers to the line will decide whether the structure holds.

What to watch

  • First gas to Abuja, which NNPC targets before the end of 2026.
  • Whether NNPC discloses the lenders and terms of the financing.
  • Signed offtake by power plants and industry in Kaduna and Kano.
  • Domestic gas sales in NUPRC's monthly reports as the line comes into use.

Methodology

The financing, the project's progress and its capacity come from NNPC's statements as reported by Arise, ThisDay, Leadership and Daily Trust; the value of the pipeline is Daily Trust's report. Gas production and domestic sales are NUPRC's provisional August 2026 figures as Dataminal carries them, converted from million to billion standard cubic feet a day.

Sources

  1. 1NNPC Secures $1.5bn Financing For AKK Pipeline, Targets Abuja Gas Supply By Year-End (opens in a new tab)Arise · 2026-11-16 · Article
  2. 2NNPC: $1.5bn Raised for AKK Gas Pipeline on Projected Throughput (opens in a new tab)ThisDay · 2026-11-16 · Article
  3. 3Nigeria Secures $1.5bn For AKK, Seeks Fresh Investment Amid 100% Pipeline AvailabilityLeadership · 2026-11-18 · Article
  4. 4Why we raised $1.5bn for AKK gas pipeline – NNPCDaily Trust · 2026-11-19 · Article
  5. 5Gas productionDatasetOn Dataminal: Nigeria Gas Production & Flaring

Related datasets

About the author

  • Dataminal ResearchResearch team

    Dataminal's research team: analysis of Nigerian markets, industries, policy and the economy, built on the datasets and sources Dataminal curates.